How The Dwyer Company Engineered High-Capacity Micro-Pile Foundations in Extreme Space Constraints

When Fairfield Water Treatment Plant required a foundation system inside an existing building capable of supporting two 31,500-pound chlorine tanks, the project presented a unique engineering challenge: access was severely restricted, with the room measuring approximately 15 feet by 20 feet and headroom limited to just 12 feet. In close collaboration with Building Crafts, Inc., The Dwyer Company deployed specialized compact equipment and installed 12 micro-piles engineered to support 30 kips each with a factor of safety of 2.5. Due to limited geotechnical analysis, a sacrificial load test was performed to verify the design before full installation. Each micro-pile extended 45 feet to reach load-bearing strata—proving that even locations with extreme access constraints and critical weight requirements can achieve structural integrity with the right attention to detail and coordination.

Quick Facts

The Challenge:

The primary challenge was installing a foundation system capable of supporting 63,000 pounds of critical equipment within an existing building with severe spatial restrictions—requiring our team to carefully navigate 15×20-foot room dimensions with only 12 feet of vertical clearance and establish stable working conditions around active water treatment infrastructure. Conventional deep foundation equipment couldn’t achieve the required 45-foot pile depths and 30-kip load capacity without extensive demolition and costly facility modifications. Additionally, limited geotechnical data increased design risk, given the critical nature of the chlorine storage system and the need for verified, fail-safe structural performance.

The Solution: High-Capacity Micro-Pile Array with Load Testing Verification

The Dwyer Company designed and installed a 12-pile micro-pile foundation system that achieved 30-kip capacity per pile despite extreme access limitations. The solution required detailed pre-installation planning, compact equipment specifications compatible with the confined workspace, and careful coordination with ongoing water treatment operations.

The installation process involved mobilizing a specialized compact excavator capable of operating in the restricted 15×20-foot footprint, executing precision drilling operations to 45-foot depths with minimal clearance requirements, and implementing a sacrificial load test on the first pile to verify design assumptions before proceeding with full installation. Each micro-pile was installed to exacting specifications to ensure load distribution across the array and provide the factor of safety required for this critical chemical storage application.

The entire installation maintained the facility’s operational schedule, providing Fairfield Water Treatment Plant with a permanently engineered foundation system and eliminating the risk of structural failure or settlement under the substantial loads imposed by dual chlorine tanks.

Key Project Details

Load Capacity

with 12 micro-piles engineered for 30 kips each, supporting 63,000 pounds with substantial safety margin

0 kips total

Pile Depth

lengths extending to competent bearing strata verified through load testing

0 ft

Safety Factor

factor of safety applied due to limited geotechnical analysis, ensuring conservative design

0

Load Testing

Sacrificial test pile conducted to verify capacity assumptions before full installation

Access Constraints

Installation completed within 15×20-foot room with 12-foot ceiling using compact specialized equipment

Coordination Excellence

Seamless collaboration with Building Crafts, Inc. to maintain water treatment facility operations throughout installation

Why Micro-piles?

The Dwyer Company’s micro-pile foundation system delivered the load capacity and installation flexibility required for this constrained, high-consequence project.

The Impact: Mission-Critical Infrastructure with Zero Compromise

Cost-Effective Solution

The micro-pile system eliminated expensive building modifications, demolition, and reconstruction that conventional foundation methods would have required, delivering budget optimization while meeting rigorous structural performance standards.

Schedule Preservation

Completing the foundation installation within operational windows prevented delays to the chlorine system upgrade and maintained uninterrupted water treatment services for the community.

Zero Structural Settlement

Most critically, the verified load testing and engineered design delivered absolute structural certainty for a foundation system supporting hazardous chemical storage—providing Fairfield Water Treatment Plant with a permanently stable, fail-safe foundation that will support decades of critical infrastructure operations with zero risk of settlement or structural failure.

Why Choose The Dwyer Company for Structural Integrity?

Deep History • Solid Choice

The Dwyer Company’s proven track record in commercial and industrial foundation systems made us the trusted partner for this critical infrastructure project. Our team’s technical expertise, advanced equipment, and commitment to precision execution delivered a foundation system that will support decades of heavy industrial use.

Call The Dwyer Company and one of our experts will get you taken care of with an accurate inspection quote!

Call The Dwyer Company and one of our experts will get you taken care of with an accurate inspection quote!