How The Dwyer Company Stabilized a Settling Classroom Addition at Boone Grove High School

An addition at Boone Grove High School in Valparaiso, Indiana was settling, and the movement had taken the foundation and a classroom slab with it. The Dwyer Company installed 11 helical underpins to stabilize the addition, working with general contractor Gibson-Lewis Contractors and engineer Civil Solutions. Each underpin was designed to support 15 kips at depths between 21 and 28 feet. The design started at 5 underpins, and what the open excavations showed brought the count to 11. The work took one week.

Watching a classroom addition settle?

Quick Facts

The Challenge

The addition had settled far enough to pull down the foundation and a classroom slab. The original design called for 5 helical underpins. Dwyer made a site visit, and once the excavations were open the picture changed.

Two things turned up in those excavations. Existing helical underpins already sat on the footer, so the new spacing had to work around them. A disconnected waterline showed up at the addition as well. Dwyer’s read is that the soft soils and that waterline together drove the failure, and the 5 underpins on the drawings would not cover what the building needed.

Key Project Details

helical underpins installed to stabilize the settling addition

0

kips supported per underpin

0
Underpins installed at depths between 21 and 28 feet
Helical Anchors Inc material, 2-7/8 inch shaft with a 12-14 helix configuration
Design increased from 5 underpins to 11 after the excavations were exposed
Full scope completed in 1 week

The Solution: Helical Pier Foundation System

The Dwyer Company installed 11 helical underpins along the addition’s footer, each designed to support 15 kips at depths between 21 and 28 feet. All of them used Helical Anchors Inc material on a 2-7/8 inch shaft with a 12-14 helix configuration, which put the addition on support well below the soils that had been giving way.

Spacing was the field problem. Existing underpins already occupied part of the footer, so every new location had to fall between them and still land where the settlement called for support. Dwyer recommended the higher count after the site visit and carried the change through with Gibson-Lewis Contractors and Civil Solutions. The stabilization closed in a week.

The Impact

Eleven underpins took a settling classroom addition off soils that had stopped holding it.

Support carried to 21 to 28 feet

Each underpin advanced until it met its 15 kip design capacity below the soft soils.

Count matched to what the excavations showed

The recommendation to go from 5 underpins to 11 came out of the site visit, before the work was set.

Existing underpinning worked around

New locations were spaced between the underpins already attached to the footer.

One week on site

The full 11-underpin scope was installed inside a one-week window.

Why Helical Underpinning?

Helical underpins let The Dwyer Company add capacity to a settling footer that already had piers on it, without taking apart what was there.

  • Works alongside existing underpinning – New units can be spaced between piers already attached to a footer.
  • Installed to capacity – Each underpin advances until it meets its design load, so depth follows the soils.
  • Attaches at the existing footer – Support goes in at the foundation without rebuilding the structure above it.
  • Quick to install – Underpins reach capacity as they go in, which suits a short schedule window.

Why Choose The Dwyer Company for structural integrity?

Deep History • Solid Choice

The Dwyer Company’s proven track record in commercial and industrial foundation systems made us the trusted partner for the settling addition at Boone Grove High School. Working alongside Gibson-Lewis Contractors and Civil Solutions, our crew read the open excavations, recommended the support the building needed, and installed 11 helical underpins in a week.

Have a settling addition with piers already on the footer?

Call The Dwyer Company and one of our experts will get you taken care of with an accurate inspection quote!

Call The Dwyer Company and one of our experts will get you taken care of with an accurate inspection quote!