Knox Community Hospital built an addition adjacent to its existing building in Mount Vernon, Ohio, where reaching native soils with a conventional footing would have meant excavating right beside the existing footer. The Dwyer Company installed two helical piers to support a new column, working with general contractor Modern Builders, Inc. Each pier was designed to support 9 kips. The piers reduced the excavation depth and kept the new foundation from influencing the one already carrying the hospital.

Adding on next to a building you cannot afford to disturb?

Quick Facts

The Challenge

The addition went up directly against the existing hospital building. Reaching native soils with a conventional footing would have meant undercutting alongside the existing footer, which puts the support already carrying the building at risk. Two foundations set that close also influence each other, so the new column needed a load path that stayed clear of the one in place.

Access made the work harder. The pier locations sat hard against the existing wall, which limited what equipment could reach them and where it could set up.

Key Project Details

helical piers installed to support a new column for the addition

0

kips designed into each pier

0 kips
Excavation depth reduced by carrying the column on piers instead of a deep footing
Piers installed hard against the existing hospital building

The Solution: Helical Pier Foundation System

The Dwyer Company installed two helical piers under the new column. Each pier was designed to support 9 kips and carried the column load into suitable soils below. Working through the pier design let Dwyer cut how deep the crew had to dig, so the excavation stayed above the elevation where it would have undercut the existing footer.

Placement did the rest. Both piers went in tight against the existing building with equipment sized for the room available, and Dwyer coordinated the locations with Modern Builders, Inc so the new column and the existing foundation stayed out of each other’s influence.

The Impact

Two piers carried a new column immediately beside an existing hospital building.

The existing footer stayed undisturbed

Carrying the column on piers removed the undercutting that reaching native soils by excavation would have taken.

Foundations kept independent

The pier layout kept the new column’s load path clear of the foundation already supporting the hospital.

Shallower excavation

The pier design cut the depth the crew had to dig for the new column.

Installed in tight quarters

Both piers went in against the existing wall using the equipment the space allowed.

Why Helical Piers?

Helical piers let The Dwyer Company carry a new column into suitable soils beside a hospital where deep excavation next to the existing footer was off the table.

  • Protects adjacent foundations – Piers transfer load below grade without an open cut alongside an existing footer.
  • Shallower excavation – The load path runs down through the pier, so the footing above it can stay shallow.
  • Small equipment footprint – Compact machines reach locations set hard against an existing wall.
  • Designed capacity per pier – Each pier is specified to a load, so the foundation matches what the column puts on it.

Why Choose The Dwyer Company for structural integrity?

Deep History • Solid Choice

The Dwyer Company’s proven track record in commercial and industrial foundation systems made us the trusted partner for the addition at Knox Community Hospital. Working alongside Modern Builders, Inc, our crew set two helical piers tight against the existing building and gave the new column support on suitable soils.

Have an addition going up against an occupied building?

Call The Dwyer Company and one of our experts will get you taken care of with an accurate inspection quote!

Call The Dwyer Company and one of our experts will get you taken care of with an accurate inspection quote!